Title
An ordinance approving and authorizing the execution of a contract with NFT Group LLC, for St. Charles Parish Courthouse 2nd Floor Renovation, (Project No. GBCH0518), in the amount of $6,179,000.00.
Body
WHEREAS, Ordinance No. 18-5-9 adopted on May 21, 2018, by the St. Charles Parish Council approved and authorized the execution of a Professional Services Contract with Murray Architects for the design and construction management of the renovation of the second floor within the St. Charles Parish Courthouse Building in Hahnville; and,
WHEREAS, sealed bids were received by St. Charles Parish on May 12, 2022, for St. Charles Parish 2nd Floor Renovation (Project No. GBCH0518); and,
WHEREAS, Murray Architects has reviewed the bids and recommends that the contract be awarded to the low bidder, NFT Group LLC, in the amount of $6,179,000.00; and,
WHEREAS, these renovations will provide three adequate size courtrooms which allows for better docket planning and court scheduling in the judicial system.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That the bid of NFT Group LLC, for the construction of St. Charles Parish Courthouse 2nd Floor Renovation, (Project No. GBCH0518) is hereby approved and accepted in the amount of $6,179,000.00.
SECTION II. That the Parish President is hereby authorized to execute said contract on behalf of St. Charles Parish.
SECTION III. A final Notice of Contract shall be printed and filed in place of the contract documents with the St. Charles Parish Clerk of Court and in the records of the St. Charles Parish Council.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this day of , 2022, to become effective five (5) days after publication in the Official Journal.