An ordinance approving and authorizing the execution of Change Order No. 1 (final) for the Renovations to the 3rd floor of the Courthouse Project to add ninety-two (92) additional days to the contract and increase the contract amount by $53,230.10.
Body
WHEREAS, Ordinance No. 14-9-6 adopted September 2, 2014 by the St. Charles Parish Council awarded construction of the Renovations to the 3rd floor of the Courthouse, St. Charles Parish Project #P080402 to BATTCO Construction & Maintenance Inc; and,
WHEREAS, additional work in the amount of $53,230.10 was necessary to ensure proper modernization was realized in the areas formerly housing the jail and time delays associated with such work and courthouse scheduling necessitates the additional ninety-two (92) days.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 1 (final) for the Renovations to the 3rd floor of the Courthouse Project to add ninety-two (92) additional days to the contract, and increase the contract amount by $53,230.10 is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this ____ day of ________, 2015, to become effective five (5) days after this publication in the official journal.
CHAIRMAN:_________________________________________
SECRETARY:________________________________________
DLVD/PARISH PRESIDENT:____________________________
APPROVED:______________ DISAPPROVED:_____________
PARISH PRESIDENT:_________________________________
RETD/SECRETARY:__________________________________
AT:_______________ RECD BY: ________________________