2002-0442
INTRODUCDED BY: ALBERT D. LAQUE, PARISH PRESIDENT
(DEPARTMENT OF PUBLIC WORKS)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. One (1) - Final for Parish Project No. P000311, Bar None Jack & Bore, to purchase materials from contractor and close out the project prior to the commencement of construction.
Body
WHEREAS, Ordinance No. 02-2-5, adopted February 21, 2002, by the St. Charles Parish Council awarded construction of Parish Project No. P000311, Bar None Jack & Bore, to B & K Construction Company, Inc.; and
WHEREAS, there were a significant number of utility conflicts requiring relocation; and
WHEREAS, Illinois Central/ Canadian National Railroad has been uncooperative in resolving the utility conflicts within the railroad right-of-way; and
WHEREAS, B & K Construction Company, Inc. has missed its window of opportunity for project construction and has requested release from its contract; and
WHEREAS, approval of this change order is necessary to close out the contract with B & K Construction Company, Inc. and re-bid the project in order to award it to another contractor.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS,
SECTION I. That Change Order No. One (1) - Final to Parish Project No. P000311, Bar None Jack & Bore, to release B & K Construction Company, Inc. for its contract and purchase various project materials is hereby approved.
SECTION II. That the Parish President is hereby authorized to execute said Change Order.
Vote
The foregoing ordinance having been submitted to a vote, the vote thereon was as follows:
And the ordinance was declared adopted this _____ day of ___________, 2002,
To become effective five (5) days after publication in the Official Journal.
CHAIRMAN:______________________________________________
SECRETARY:_____________________________________________
DLVD/PARISH PRESIDENT:_________________________________
APPROVED:______________...