Title: An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for the Hurricane Gustav/Ike Community Development Block Grant (CDBG) Disaster Recovery Program Project No. 45PARA3201, the Edward A. Dufresne Community Center, to decrease the contract amount by $44,576.14 and increase the contract time by sixteen (16) days.
Sponsors: V.J. St. Pierre Jr., Grants Office
Indexes: Community Center (formerly: P and R (Dept. of) (Civic Center), Community Dev. Block Grant
Attachments: 1. Change Order No. 2 (Final) - Version for Publication.pdf, 2. 2013-0343 Change Order-F, 3. 2013-0343 Final Ord 13-10-4 with Change Order
Related files: 2013-0472, 2012-0447, 2011-0371, 2010-0409, 2010-0401, 2010-0283, 2010-0135, 2010-0084, 2004-0402, 2004-0271, 2017-0137, 2014-0121, 2014-0071, 2011-0373, 2015-0228, 2017-0286, 2019-0003, 2020-0112, 2023-0030
2013-0343
INTRODUCED BY: V.J. ST. PIERRE, JR., PARISH PRESIDENT
(GRANTS OFFICE)
ORDINANCE NO.
Title
An ordinance approving and authorizing the execution of Change Order No. 2 (Final) for the Hurricane Gustav/Ike Community Development Block Grant (CDBG) Disaster Recovery Program Project No. 45PARA3201, the Edward A. Dufresne Community Center, to decrease the contract amount by $44,576.14 and increase the contract time by sixteen (16) days.
Body
WHEREAS, Ordinance No. 11-12-2, adopted December 5, 2011, by the St. Charles Parish Council, approved and authorized the execution of a contract with Lamar Contractors, Inc., for the Edward A. Dufresne Community Center in the amount of $10,565,980.00; and,
WHEREAS, Ordinance No. 13-1-5, adopted January 7, 2013, by the St. Charles Parish Council, approved and authorized Change Order No. 1 to decrease the contract amount by $373.78 and increase the contract time by thirty-five (35) days; and,
WHEREAS, the decrease in contract amount from Change Order No. 2 (Final) is a result of a combination of the application of the remainder of a sales tax exemption credit due from said contractor and the Unforeseen Allowance towards the cost of change directives; and,
WHEREAS, the increase in contract time is a result of sixteen (16) days related to change directives.
THE ST. CHARLES PARISH COUNCIL HEREBY ORDAINS:
SECTION I. That Change Order No. 2 (Final) for the Hurricane Gustav/Ike Community Development Block Grant (CDBG) Disaster Recovery Program Project No. 45PARA3201, the Edward A. Dufresne Community Center, to decrease the contract amount by $44,576.14 and increase the contract time by sixteen (16) days, is hereby approved and accepted.
SECTION II. That the Parish President is hereby authorized to execute said Change Order on behalf of St. Charles Parish.
Vote